Colorado Produce Company leases property and building from Karmadad
LLC Building permits purchased and first phases of construction completed Site work and excavation for all phases completed
Gravel parking lots, parking lot lights, security system for existing and beginning grow substantially completed
Gated entrance, fencing and perimeter retaining walls and security fence
substantially completed All concrete footings and foundations completed for Phase 1 Phase 1, 51,680 sf pre-engineered building package #1 is onsite, ready to erect Estimated property value will be over 7 million after completion of
Phase 1 building • Foundation and foundation walls for processing area completed Granted and approved for Phase 1, 2, and 3